Project Notices

For notices related to the North Campus Infrastructure project, please visit the North Campus Infrastructure Construction notices page.

Construction Notice – NE01 3rd Floor Railing

Construction Schedule: 11:00 pm to 6:00 am from August 8, 2018 to September 7, 2018
Location: NE01 3rd Floor
Description of Project: Replacing railing panels
Customer Impact: Fencing around public hallway, minor construction noise and traffic on site
Contractor: Kinetic Construction
Consultant: Colborne Architectural Group

If you have any question about this scheduled construction, please contact Sally Han at 604-456-1147 or jhan15@bcit.ca

Construction Notice – SW01 Gateway Deli (2303)

Construction Schedule: August 1, 2018 to August 22, 2018
Location: SW01 Gateway Deli
Description of Project: Counter and food display renovations
Customer Impact: Noise, temporary impacts to certain food offerings
Contractor: Reco Decoration Group Inc.

If you have any question about this scheduled construction, please contact Dominic Cuthbertson at 778-945-6137 or dcuthbertson@binnie.com

Construction Notice – SE02 Rix Club Renovations

Construction Schedule: July 27, 2018 to August 27, 2018
Location: SE02 Rix Club
Description of Project: Counter and food display renovations
Customer Impact: Noise, temporary impacts to certain food offerings
Contractor: Reco Decoration Group Inc.

If you have any question about this scheduled construction, please contact Dominic Cuthbertson at 778-945-6137 or dcuthbertson@binnie.com

Construction Notice – SW09-115D Storage Room

Construction Schedule: July 26, 2018 to August 20, 2018
Location: Burnaby Campus, SW09-115D Storage Room
Description of Project: Remove sink & faucet, remove cabinets, repair drywall, and paint.
Customer Impact: Some construction noise
Contractor: Eco-Sol Reinstatement Solutions Inc.

If you have any question about this scheduled construction, please contact Susan Maclaren at 604-456-8104 or smaclaren1@bcit.ca

Construction Notice – SW03 – Classroom 1920

Construction Schedule: July 26, 2018 to August 20, 2018
Location: Burnaby Campus, SW03 – classroom 1920
Description of Project: Remove cabinets, repair drywall, and paint.
Customer Impact: Some construction noise
Contractor: Eco-Sol Reinstatement Solutions Inc.

If you have any question about this scheduled construction, please contact Susan Maclaren at 604-456-8104 or smaclaren1@bcit.ca

Construction Notice – SW01 Labs 1230 and 1240

Construction Schedule: July 26, 2018 to August 20, 2018
Location: Burnaby Campus, SW01 – Labs 1230 and 1240
Description of Project: Replace cabinet door and drawer fronts with new.
Customer Impact: Some construction noise
Contractor: Eco-Sol Reinstatement Solutions Inc.

If you have any question about this scheduled construction, please contact Susan Maclaren at 604-456-8104 or smaclaren1@bcit.ca

Construction Notice – NE01 Studio Classroom 407B

Construction Schedule: July 26, 2018 to August 20, 2018
Location: Burnaby Campus, NE01 – Room 407B
Description of Project: Remove millwork, lower some electrical receptacles, repair drywall, paint, and install new whiteboards.
Customer Impact: Some construction noise
Contractor: Eco-Sol Reinstatement Solutions Inc.

If you have any question about this scheduled construction, please contact Susan Maclaren at 604-456-8104 or smaclaren1@bcit.ca

Construction Notice – NE01 Classroom 353

Construction Schedule: July 26, 2018 to August 20, 2018
Location: Burnaby Campus, NE01 – Room 353
Description of Project: Raise some electrical receptacles, repair drywall, paint, and install millwork cabinets.
Customer Impact: Some construction noise
Contractor: Eco-Sol Reinstatement Solutions Inc.

If you have any question about this scheduled construction, please contact Susan Maclaren at 604-456-8104 or smaclaren1@bcit.ca

Construction Notice – NE01 Resource Room 316

Construction Schedule: July 26, 2018 to August 20, 2018
Location: Burnaby Campus, NE01 – Room 316
Description of Project: Replace flooring, upgrade the ventilation, minor electrical, painting, and millwork.
Customer Impact: Some construction noise
Contractor: Eco-Sol Reinstatement Solutions Inc.

If you have any question about this scheduled construction, please contact Susan Maclaren at 604-456-8104 or smaclaren1@bcit.ca

Construction Notice – Marine Campus – Classroom 240

Construction Schedule: July 23, 2018 to August 16, 2018
Location: Marine Campus – Room 240
Description of Project: Upgrade electrical, data connections, new t-bar ceiling and paint walls in Room 240 Simulation Lab.
Customer Impact: Some construction noise
Contractor: Seyers Electric Contractors Limited

If you have any question about this scheduled construction, please contact Gina Ng at 604-432-8909 or gina_ng@bcit.ca

Construction Notice – SW02 Re-roofing

Construction Schedule: July 24, 2018 to August 16, 2018
Location: SW02 Roof
Description of Project: Removal and replacement of the existing roofing membrane
Customer Impact: Noise, temporary Heating Ventilation and Air Conditioning (HVAC) shutdowns
Contractor: Bothwell-Accurate Company Ltd.

If you have any question about this scheduled construction, please contact Dominic Cuthbertson at 778-945-6137 or dcuthbertson@binnie.com

Construction Notice – SW13 Unit D (Carrier House)

Construction Schedule: July 3, 2018 to August 20, 2018
Location: SW13 Unit D, 4th floor
Description of Project: Interior renovation of 4th floor to make the unit accessible to persons with disabilities
Customer Impact: Construction noise and traffic on site 
Contractor: Finlink Construction Ltd.
Consultant: The Colborne Architectural Group Pacific Inc.

If you have any question about this scheduled construction, please contact Susan Maclaren at smaclaren1@bcit.ca

Construction Notice – SE12 Room 305 and 307

Construction Schedule: July 3, 2018 to August 10, 2018
Location: SE12 Room 305 and 307
Description of Project: Interior renovation of classroom 307 and demolition of storage room 305
Customer Impact: Hoarding in hallway. Minor construction noise and traffic on site
Contractor: Finlink Construction Ltd.
Consultant: DA Architects

If you have any question about this scheduled construction, please contact Sally Han at 604-456-1147 or jhan15@bcit.ca or Susan Maclaren at smaclaren1@bcit.ca

Construction Notice - DTC 6th Floor Renovations

Construction Schedule: April 1, 2018 to August 31, 2018
Description of Project: Renovations to various classrooms Rooms 645, 652, 655, 665, 666, 667, 668, 669, 676, and 678, on north side of 6th floor at downtown campus. Flooring replacement, millwork replacement, lighting replacement, renovations to doors mechanical and electrical systems, and classroom walls.
Contractor: Holaco Construction
Consultant: DA Architects
Customer Impact: Minimum impact to users and occupants

If you have any questions about this scheduled construction project, please contact Ryan Jacobs @ 604-456-1096 or rjacobs13@bcit.ca

Construction Notice – SW02 & SW03 Re-roofing

Construction Schedule: June 11, 2018 to September 7, 2018
Location: SW02 & SW03 Roof
Description of Project: Removal and replacement of the existing roofing membrane
Customer Impact: Noise, temporary Heating Ventilation and Air Conditioning (HVAC) shutdowns
Contractor: Bothwell-Accurate Company Ltd.

If you have any question about this scheduled construction, please contact Dominic Cuthbertson at 778-945-6137 or dcuthbertson@binnie.com

Construction Notice – SE08 Ventilation Upgrade

Construction Schedule: June 4, 2018 to August 24, 2018
Location: SE08 rooms 101, 102B, 201 and roof
Description of Project: Upgrading the welding exhaust system to meet current Codes, industry best practices, and BCIT Technical Standards
Customer Impact: Classroom closures and minor noise
Contractor: Holaco Construction Ltd.

If you have any question about this scheduled construction, please contact Dominic Cuthbertson at 778-945-6137 or dcuthbertson@binnie.com

Construction Notice – SE02 Refrigeration Retrofit

Construction Schedule: June 19, 2018 to September 4, 2018
Location: SE02 loading dock and roof, (1) interior refrigeration unit
Description of Project: Remove and replace existing refrigeration units on loading dock including associated architectural, structural, mechanical and electrical work. Refurbishment of interior refrigeration unit.
Customer Impact: Use of temporary refrigeration units during construction
Contractor: Smith Bros. & Wilson Ltd.

If you have any question about this scheduled construction, please contact Dominic Cuthbertson at 778-945-6137 or dcuthbertson@binnie.com