Project Notices

For notices related to the North Campus Infrastructure project, please visit the North Campus Infrastructure Construction notices page.

Installation Notice - SE2 hallway vinyl wall decal

Installation Schedule: Wednesday, May 16, 2018
Location: SE2 hallway, south side of Town Square B (SE2-212B)
Description of installation: Vinyl wall decal installation.
Contractor: National Graphics Solutions Inc. (NGSI)
Customer Impact: Minimal to no impact as the installation is scheduled for end of day. The installer will be working on one side of the hallway wall, applying the vinyl decal display.

If you have any question about this scheduled installation, please contact Joni Louie at joni_louie@bcit.ca

Construction Start – Downtown Campus, Level 3 Washroom Renovations

Construction Schedule: From May 2, 2018 to July 10, 2018
Location: Level 3 Main Male and Female Washrooms
Description of Project:Remove existing plumbing fixtures, electrical fixtures, partitions, flooring, and replace with new. Install new tile and decorative panels to walls.
Contractor: Kinetic Construction
Consultant: DA Architects and Planners
Customer Impact: The level 3 washrooms will be out of service until the renovation is complete. There will be contractors present on the 3rd floor until the renovation is complete. Floor protection will be installed outside the 3rd level washrooms and main corridor.

If you have any question about this scheduled construction, please contact Ryan Jacobs 778-554-1163 or rjacobs13@bcit.ca

Construction Start – Downtown Campus, Cooling Tower Replacement

Construction Schedule: From April 16, 2018 To May 11, 2018
Location: Roof and Penthouse Mechanical Room
Description of Project:Removal and replacement of the cooling tower and associated infrastructure.
Contractor: ESC Automation
Consultant: Rocky Point Engineering Ltd.
Customer Impact: Mild periodic construction noise may be heard on the 8th floor. Possible temporary increase to the indoor air temperature between May 5 - 10, 2018

If you have any question about this scheduled construction, please contact Ryan Jacobs, Project Manager, 778-554-1163 or rjacobs13@bcit.ca

Construction Notice - DTC 6th Floor Renovations

Construction Schedule: April 1, 2018 to August 31, 2018
Description of Project: Renovations to various classrooms Rooms 645, 652, 655, 665, 666, 667, 668, 669, 676, and 678, on north side of 6th floor at downtown campus. Flooring replacement, millwork replacement, lighting replacement, renovations to doors mechanical and electrical systems, and classroom walls.
Contractor: Holaco Construction
Consultant: DA Architects
Customer Impact: Minimum impact to users and occupants

If you have any questions about this scheduled construction project, please contact Gary Holtz @ 604-432-8651 or gholtz1@bcit.ca