NE25 Envelope

Location: Building NE25

Impacts of Interruption: Access to interior rooms, minor and major construction noise, access to building maybe re-routed

Scope of work: Power washing NE25 exterior, window replacement in offices and stairwells, recaulking and repainting windows, floor replacement in both stairwells, repainting guardrails in both stairwells, wall repairs in both stairwells.

Impacts expected: All building NE25 users

Construction period: Work to be completed between July 20th and September 25th, 2020

Project Services Contact: Allana Spooner, Email: aspooner6@bcit.ca

 

SE01 Envelope and Courtyard Renew

Location: Building SE01

Impacts of Interruption: Access to interior rooms, minor and major construction noise, access to building maybe re-routed

Scope of work: Concrete repair of cracks, spalls and delamination, supply and installation of metal flashings, removal and replacement of exterior sealants, including joint accessories, exterior power cleaning, application of clear sealer, and painting of exterior elements and columns, and application of elastomeric coatings on stucco.

Impacts expected: All building SE01 customers and users

Construction period: Tuesday, July 22 to August 31, 2020

Project Services Contact: Tim Wong,  Email: tim_wong@bcit.ca